First, plan a realistic timeline. You should allow about two days for demolishing the old bathroom and two days eachfor carpentry, plumbing, flooring and drywall. Tiling usually takes the longest: about three days. Elements such as cabinets, fixtures, insulation, drywall and electrical work usually do not take more than a day. You are looking at roughly two weeks, but allowing for extra time is never a bad idea when it comes to NJ home remodeling.
Decide on tiling, wallpaper styles and a color scheme. Whites and grays tend to give bathrooms a sleek, modern appearance that some find appealing. Others, however, want a bathroom full of rich colors like red or lavender.
The last step is to draw a sketch. Consider the placements of lights and mirrors, take accurate measurements of your bathroom space and draw your plan to scale. This will help the professionals carry out your vision.
Take these steps and your bathroom renovations should be a breeze.